Infraconcrete← Back to home
Solutions · Earthworks

Earthworks contractor in Malaysia.

Cut and fill, mass haul, platform creation, hillside development earthworks, integrated with retaining walls, drainage, and slope stabilization as one specialist package. CIDB G7. ISO 9001:2015. Bandar Serendah 540,000 m³ backfill delivered; Bandar Batu 18 Semenyih 120,000 m³ earthworks plus 11,000 m² retaining wall as a single coordinated scope.

540,000 m³
Bandar Serendah
120,000 m³
Bandar Batu 18
100+
Projects delivered
G7
CIDB highest grade
Engineer's note Cut + fill + compaction + ground treatment for platforms, embankments, road formations. CIDB G7 + integrated with retaining + slope works as one design-build package. Send the master plan for scope + programme. WhatsApp the engineering team →
01 / What we deliver

Earthworks plus everything that holds it.

Earthworks transform a site's natural landscape into stable, buildable platforms. The work covers cutting from high ground, hauling to fill ground, compacting to design density, and the drainage that makes the platform durable. The biggest challenge in Malaysia: tropical soft and saturated soils, lateritic ground, and the compaction quality needed for heavy permanent loads.

We integrate earthworks with slope stabilization and retaining walls as one package. That's why Bandar Serendah (540,000 m³) and Bandar Batu 18 (120,000 m³ earthworks + 11,000 m² retaining wall) were delivered without interface gaps between trades.

Cut and fill, mass haul

Cutting from high ground, hauling to fill, compaction to design density. Heavy plant for large volumes.

Platform creation

Hillside ground transformed into buildable platforms. Stabilized cut slopes, retaining walls between platforms, slope protection.

Drainage and trenches

Site drainage, perimeter drains, sediment traps, horizontal drains, U/V-drains. Integrated with earthworks.

Internal roads and access

Site spine roads, access roads, embankments, heavy compaction, edge drainage, durable construction.

03 / FAQ

Developers and engineers usually ask:

Earthworks scope? +
Cut and fill, mass haul, platform creation, hillside earthworks, road and drainage earthworks, basement excavation. Integrated with retaining walls and slope stabilization.
Standards? +
BS 6031, JKR specifications, ESCP compliance. Compaction by Proctor, field density, CBR per spec.
Programme? +
100,000 m³ typically 3-6 months. Bandar Serendah-scale (540,000 m³+) runs 12 months+.
Drainage and ESCP? +
Yes. Drainage, sediment traps, silt traps, ESCP submissions, DOE/JAS compliance, part of the earthworks scope.
Earthworks + retaining + slope as one package? +
Yes, our default. Bandar Batu 18 and Bandar Serendah are examples.
04 / Standards we work to

Codes and government specs.

StandardCoverage
BS 6031Earthworks, Code of practice
BS 1377Methods of test for soils for civil engineering
BS 5930Code of practice for ground investigations
BS EN 1997 (Eurocode 7)Geotechnical design, partial-factor
JKR-SPJ Section 2Earthworks, JKR Standard Specifications for Highway Works
MS 1227Malaysian standard for soil compaction

Compaction control per JKR / BS 1377: 95% MDD for general fill, 98% for structural backfill. Field density via nuclear gauge (Troxler), sand-replacement, or DCP. Records signed off per layer, per location, per ITP.

05 / Plant, Crew, and Production

Equipment, fill rates, programme drivers.

Earthworks production rate is the single biggest programme variable on a development. Plant selection, crew sizing, and lift discipline determine whether the platform handover lands ahead of schedule or pushes the whole construction sequence behind. The ranges below cover the bulk of Malaysian residential, township, and industrial earthworks scope.

Excavation and haulage plant

  • 20-tonne excavator (Komatsu PC200-class, CAT 320, Hitachi ZX200): primary digger for residential and small township scopes. Production rate typical 80 to 150 m³ per hour in residual soil, less in stiff clay.
  • 50-tonne excavator (PC400, CAT 374, ZX490): bulk earthworks for large township and industrial platforms. Production rate 250 to 400 m³ per hour in residual soil. One unit typically replaces 2 to 3 PC200s.
  • 30-tonne articulated dump truck (ADT): standard haulage for on-site material movement on uneven ground. Cycle time site-dependent (haul distance, gradient, intersection management).
  • 50-tonne ADT: long-haul or high-volume sites. Better load-per-cycle but needs better haul-road maintenance.
  • Bulldozer (D8, D9-class): grading, spreading, dozing of fill from stockpile to placement zone. Often paired with motor grader for the final fine-trim.

Compaction plant (matched to fill type)

  • Smooth-drum vibratory roller (12 to 22 tonne static, Hamm, Bomag, CAT): granular fill, gravel, well-graded sand. The default for Malaysian residual soil fill at correct moisture.
  • Padfoot (sheepsfoot) roller: cohesive fill (clay, silty clay). The padfeet kneed the clay and increase the contact pressure that drives compaction in cohesive soils.
  • Pneumatic-tyre (PTR) roller: subgrade dressing, fine fill compaction, pavement preparation.
  • Vibratory plate compactor: tight-access zones (around services, in trench backfill, against retaining walls where the roller cannot reach).

Crew composition

Typical core crew for a 50,000 to 200,000 m³ earthworks scope: 1 project manager, 1 site engineer, 1 surveyor (full-time GPS / total station), 1 safety officer, 1 QC engineer, plus operators per plant inventory (typically 1 operator per machine plus 1 spare). For township-scale (500,000 m³+), scale up to 2 site engineers, 2 surveyors, separate QA and HSE leads, and plant manager for inventory coordination. See construction equipment and machinery guide for the full plant reference.

Production rates (typical Malaysian conditions)

  • Bulk cut, residual soil, 50-tonne excavator + 30-tonne ADT: 2,000 to 4,000 m³ per shift
  • Bulk fill placement and compaction in 200 to 300 mm lifts: 1,500 to 3,000 m³ per shift per crew
  • Topsoil strip and stockpile: 5,000 to 10,000 m² per shift
  • Subgrade preparation and final trim: 3,000 to 6,000 m² per shift

Programme drivers

The four most common Malaysian earthworks programme drivers: (1) Monsoon season (November to March on the East Coast, October to December across Peninsular interior) cuts production by 30 to 60 percent due to wet ground refusal. (2) Cut-fill imbalance requiring import or disposal, with the cost and logistics. (3) Refusal in unexpected hard ground (rock, boulders, residual rock outcrops) needing breaker plant or pre-blasting. (4) DOE Erosion and Sediment Control Plan (ESCP) compliance during the works, which can pause production after heavy rainfall events. See the cost and programme guide for the full framework.

Plant productivity table

OperationPlant pairIndicative production
Topsoil stripDozer + PC200 + ADT5,000 to 10,000 m² / shift
Bulk cut (residual soil)PC400 + 30T ADT (x3)2,000 to 4,000 m³ / shift
Bulk fill in 250 mm liftsDozer + 12T smooth-drum1,500 to 3,000 m³ / shift
Compaction (cohesive fill)22T padfoot1,000 to 2,500 m³ / shift
Subgrade preparationMotor grader + PTR roller3,000 to 6,000 m² / shift
Hard-spot refusal handlingHydraulic breaker or pre-bore50 to 200 m³ / shift (slow)
06 / Method statement

How we deliver earthworks predictably.

01

Pre-works survey

Drone topo + GPS. Volumetric calc. Cut-fill balance check. Identify haul routes, stockpile zones, drainage.

02

Strip & clear

Topsoil strip (150-300mm), set aside for re-spread. Vegetation, existing structures, DOE-compliant disposal.

03

Cut to formation / fill in layers

Cut to design RL. Fill in 200-300mm loose layers, compact to 95-98% MDD per ITP. Moisture & density testing continuous.

04

Drainage & erosion control

Temporary drainage during works. ESCP-compliant per DOE. Permanent drainage at final levels.

05

Final survey & handover

As-built survey vs. design RL. Compaction records compiled. Defect-liability period begins.

07 / Related capabilities

Earthworks rarely works alone.

Have a site that needs to become a platform?

Send topography, the development planned, and the schedule. Same-day response with cut/fill estimate and scope.

More from Infraconcrete

Continue exploring.

Regional coverage for Earthworks

Earthworks contractor service across Malaysia. Click your state for the regional combo page, or scroll the locality cards for dedicated city / town pages:

States:Klang Valley (KL, Selangor, Putrajaya) · Johor · Penang · Pahang · Sabah · Sarawak

Klang Valley localities:Klang Valley regional hub · PJ · Cheras · Kajang · Subang Jaya · Shah Alam · Mont Kiara · Damansara · Puchong · Klang · Cyberjaya · Putrajaya · Bukit Jalil · Bangsar · Setapak · Kepong · Ampang · Selayang · Semenyih · Hulu Selangor · Bandar Sunway · USJ

Johor: Iskandar Puteri · Pasir Gudang · JB · Senai · Skudai · Kulai · Batu Pahat · Muar · Kluang · Mersing

Penang: George Town · Bayan Lepas · Butterworth · Bukit Mertajam · Tanjung Bungah · Air Itam · Balik Pulau

Other states: Kuantan · Genting Highlands · Cameron Highlands · KK · Sandakan · Tawau · Kuching · Miri · Sibu · Bintulu · Ipoh · Seremban · Bandar Melaka · Alor Setar · Kota Bharu · Kuala Terengganu · Kangar

Infraconcrete Construction Sdn Bhd
8B, Jalan SS22/25, Damansara Jaya, 47400 Petaling Jaya, Selangor, Malaysia
+60 16-428 1214 · WhatsApp · engineer@infraconcrete.co · Google Maps
CIDB G7 · ISO 9001:2015 · Sole STRATA Geosystems distributor in Malaysia (through Starwall Sdn Bhd)