Infraconcrete← Back to home
Earthworks · Design and Build · Turnkey EPC

Earthworks design and build contractor in Malaysia.

Infraconcrete Construction Sdn Bhd delivers turnkey earthworks design and build (EPC) across Malaysia. One contract carries the geotechnical and earthworks design responsibility, from ground investigation interpretation and cut and fill balance to as-built handover, plus bulk earthworks execution, plus retaining structures, plus slope stabilization, plus site drainage and erosion control. Design to BS 6031 and BS EN 1997 (Eurocode 7); compaction control to 95 percent MDD general fill and 98 percent MDD structural backfill per JKR-SPJ Section 2 and MS 1227. CIDB Grade G7 with categories CE01, CE08, CE21. Project-specific PI insurance on the design. Integrated platforms delivered including Bandar Serendah, Eco Terraces Phase 2, and Alam Impian Township.

EPC
Single-contract turnkey
G7
CIDB highest grade
PI
Insurance on the design
BS 6031
+ Eurocode 7 + JKR-SPJ
Engineering note For earthworks design and build (turnkey EPC) across Malaysia, your point of contact is the Infraconcrete engineering desk. Send the ground investigation or soil report, the survey or proposed platform layout, and the development brief. Same-day acknowledgement, with a design-and-build proposal covering cut and fill balance, retaining and slope scheme, drainage strategy, programme, and price. CIDB G7 + ISO 9001:2015 + PI insurance. WhatsApp the engineering desk →
01 / What the single contract carries

Five scope elements, one accountable party.

Earthworks on a Malaysian hillside or township platform is rarely a single trade. It combines forming the platform, retaining the levels, treating the cut slopes, and draining the whole site. In design and build, all of it sits under one contract so the design of each element is set against the others rather than tendered in silos.

Geotechnical and earthworks design

Ground investigation interpretation, cut and fill balance, platform levels, mass-haul plan, slope geometry, and temporary works. Design to BS 6031 and BS EN 1997 (Eurocode 7), with BS 5930 governing the ground investigation and BS 1377 the soil testing.

Bulk earthworks execution

Topsoil strip and stockpile, bulk cut, fill placement and compaction in 200 to 300 mm lifts, subgrade preparation and final trim. Compaction to 95 percent MDD general fill and 98 percent MDD structural backfill per JKR-SPJ Section 2 and MS 1227.

Retaining structures

Reinforced earth (RE) walls, gravity, cantilever, and gabion. The wall type is chosen to suit the ground, the fill available on site, and the platform geometry, rather than fixed before the earthworks design is settled. Facing detail integrated with the drainage.

Slope stabilization

Soil nailing, shotcrete facing, and horizontal drains applied to the cut slopes the earthworks form. Designed and built as part of the same package so reinforcement, facing, and groundwater control are coordinated, not split across separate subcontracts.

Site drainage and erosion control

Surface drains, interceptor drains at cut crests, cascades and chutes, silt traps, and detention ponds. Erosion and Sediment Control Plan (ESCP) measures for DOE compliance, staged so the platform stays drained through the monsoon.

02 / Why the design and build route

Where single-contract delivery earns its keep.

  1. Single accountability. One entity is responsible for both the earthworks design and its construction. When platform levels, settlement, or slope performance are questioned, there is no design-versus-build blame gap and one party stands behind the outcome, backed by project-specific PI insurance on the design.
  2. Faster interface resolution. Ground rarely matches the SI report exactly. When a soft pocket, a hidden boulder, or a higher water table appears, the design team sits on the contractor side, so a revised cut line, a changed retaining type, or an added drain is redesigned in days rather than through the weeks a separate consultant loop can take.
  3. Buildability-led design. The cut and fill scheme is set around what the plant fleet and crew can actually build economically. Mass-haul is optimised for haul distance to cut external cart-away and import, and platform sequencing is set to keep working areas drained and trafficable.
  4. Compressed programme. Design and enabling works overlap under one programme. Site clearing, access, and ESCP silt-control works can start while platform design and authority submissions are finalised, because the designer and builder are one team.
03 / Design scope we take responsibility for

What the design package actually delivers.

Design trackWhat it covers
Ground modelSI interpretation from boreholes and probing per BS 5930, soil classification and parameters from BS 1377 laboratory testing, groundwater regime, and founding-stratum assessment.
Cut and fill balanceEarthwork volumes, mass-haul diagram, cut-to-fill matching to minimise import and cart-away, and stockpile and borrow strategy.
Platform and levelsFinished platform levels, sub-platform build-up, subgrade CBR target, and settlement assessment for structural areas.
Retaining schemeWall type selection (RE, gravity, cantilever, gabion), geometry, global and internal stability, and drainage behind the facing.
Slope treatmentCut slope geometry, factor of safety check, and soil nailing, shotcrete, or horizontal drain design where a slope needs reinforcement or groundwater control.
Drainage and ESCPSurface and subsurface drainage layout, interceptor drains, detention or sediment ponds, and the erosion and sediment control plan for DOE compliance.
Temporary worksBattered temporary faces, dewatering, haul roads, and sequencing method statements for staged construction.

Integrated output: a single earthworks design report with consistent ground assumptions, drawings covering platform, retaining, slope, and drainage, a construction sequence, a QA and compaction-testing programme, and the authority submission package. For the engineering background see the geotechnical design guide.

04 / Standards and compaction control

Codes governing the design and build.

StandardCoverage
BS 6031Code of practice for earthworks (primary execution code)
BS EN 1997 (Eurocode 7)Geotechnical design, partial-factor method for slopes and retaining
BS 5930Code of practice for ground investigations
BS 1377Methods of test for soils for civil engineering (Proctor, CBR, classification)
MS 1227Malaysian standard for soil compaction
JKR-SPJ Section 2Federal earthworks specification for government and highway works
JKR-SPJ Section 7Slope-works specification where slope treatment is in scope
BS 8006-1Reinforced soil and RE retaining wall design where applicable

Compaction control: 95 percent MDD for general fill, 98 percent MDD for structural backfill, with maximum dry density set from the Proctor test. Field density confirmed by nuclear density gauge, sand-replacement, or dynamic cone penetrometer (DCP); CBR tested per specification. All records held under the ISO 9001:2015 quality system. See the full standards reference.

05 / Plant fleet and crew

What builds the platform.

Plant / roleFunction in the earthworks package
50-tonne excavatorBulk cut and mass excavation, loading to dump trucks, rock ripping with hydraulic breaker attachment
20-tonne excavatorGeneral cut and fill, trimming, drainage and retaining-wall excavation, working close to structures
30-tonne and 50-tonne articulated dump truck (ADT)On-site haul of cut material to fill areas and stockpiles along the mass-haul plan
BulldozerSpreading and grading of fill in lifts, stripping, and pushing to the excavator
Motor graderFine grading of platform and subgrade to design level and crossfall
Smooth-drum vibratory roller (12 to 22 tonne)Compaction of granular and general fill in 200 to 300 mm lifts
Padfoot (sheepsfoot) rollerCompaction of cohesive clay fill where a smooth drum would not knead the layer
Pneumatic-tyre (PTR) rollerSealing and final compaction of the subgrade surface
Vibratory plate compactor and hydraulic breakerConfined compaction behind retaining walls and around structures; breaking of rock and hard material

Crew structure: project manager or engineer-in-charge, site engineers, land surveyor for setting-out and level control, plant operators, banksmen and general crew, plus a QA or laboratory technician for field density and compaction records. Multi-front working for large township platforms.

06 / Production rates and programme

Indicative output per shift.

OperationTypical rateBasis
Bulk cut, residual soil2,000 to 4,000 m3 / shift50-tonne excavator plus 30-tonne ADT on a reasonable haul
Bulk fill placement and compaction1,500 to 3,000 m3 / shift per crew200 to 300 mm lifts, roller matched to fill type
Topsoil strip and stockpile5,000 to 10,000 m2 / shiftEnabling works ahead of bulk earthworks
Subgrade preparation and final trim3,000 to 6,000 m2 / shiftGrader plus roller to design level and crossfall

Rates are indicative for typical Malaysian residual soil and depend on haul distance, weather, rock content, and site access. In design and build, the programme is built around these rates so the cut and fill sequence, retaining-wall construction, and drainage installation interlock rather than clash. Wet-weather contingency and monsoon-period sequencing are set into the programme from the design stage. For a fuller treatment of costs and programming, see the cost and programme guide and the equipment and machinery guide.

07 / Integrated project track record

Platforms delivered as one package.

ProjectLocationIntegrated scope delivered
Bandar SerendahHulu Selangor540,000 m3 backfill with 7 retaining structures. Includes an industrial facility platform for a national automotive-industry account.
Eco Terraces Phase 2Semenyih (Mukim Bandar Batu 18)120,000 m3 earthworks plus 11,000 m2 retaining wall, with soil nailing on the cut slopes.
Alam Impian TownshipShah AlamEarthworks, soil improvement, soil nailing, retaining walls, drainage, and a flood detention pond across Precincts 6 to 10.
Mukim SentulKuala Lumpur5,000 m2 RE wall plus 6,000 m2 platform earthworks.
Bandar Ulu Kelang Spine RoadGombak, SelangorInternal spine road with earthworks, drainage, and retention for a terrace-cluster development.
Welbuilder Phase 5BJeram, Kuala SelangorEarthworks plus retaining wall, lots 14214 to 14223.
Mukim Rawang Mixed DevelopmentRawang, GombakMixed-development platform earthworks.

Project name, location, and scope only; client names are not disclosed per confidentiality. Full portfolio at /projects/.

08 / FAQ

Developers, consultants and main contractors usually ask:

What is earthworks design and build (turnkey EPC)? +
A procurement route where one contractor carries both the geotechnical and earthworks design responsibility and the construction. Instead of a consultant designing the platform, cut and fill scheme, retaining walls, slope treatment, and drainage, then tendering it to a separate earthworks contractor, the design-and-build contractor owns the whole chain from SI interpretation to as-built handover. It delivers a single accountable package for platform performance, under one CIDB G7 contract with project-specific PI insurance.
What does the single design and build contract cover? +
Five elements under one contract: (1) geotechnical and earthworks design (SI interpretation, cut and fill balance, platform levels, mass haul, slope geometry, temporary works); (2) bulk earthworks execution (strip, cut, fill and compaction, subgrade); (3) retaining structures (RE, gravity, cantilever, gabion); (4) slope stabilization (soil nailing, shotcrete, horizontal drains) on the cut slopes; and (5) site drainage and erosion control including ESCP for DOE compliance.
Why design and build rather than design-bid-build for earthworks? +
Three reasons. Single accountability: one party stands behind platform levels, settlement, and slope performance, so there is no design-versus-build blame gap. Faster interface resolution: when the ground differs from the SI report, the design team is on the contractor side, so redesign happens in days not weeks. Buildability-led design: the cut and fill scheme is set around what the plant and crew can build economically, with mass-haul optimised for haul distance. Design-bid-build still suits projects where a separate consultant must design for multiple tendering contractors.
What CIDB grade and categories do you hold? +
CIDB Grade G7 (highest contractor grade, no upper tender value limit). Categories CE01 (earthworks), CE08 (slope works), CE21 (geotechnical), B04 (specialised building works), M15 (mechanical). This combination lets one contract carry earthworks, retaining, and slope scope without splitting categories. PPK Registration 0120220822-WP104845, valid 22 August 2022 to 13 December 2027. ISO 9001:2015 certified, verifiable at cidb.gov.my.
What compaction and testing standard do you build to? +
95 percent MDD for general fill and 98 percent MDD for structural backfill, with maximum dry density set from the Proctor test per BS 1377. Field density confirmed by nuclear density gauge, sand-replacement, or DCP; CBR tested per specification. Execution follows BS 6031 and JKR-SPJ Section 2, with soil compaction to MS 1227. Records held under ISO 9001:2015 and submitted for sign-off before the layer above proceeds.
Do you carry PI insurance for the design responsibility? +
Yes. For design and build, project-specific Professional Indemnity (PI) insurance covers the design negligence exposure the contractor takes on by carrying the geotechnical and earthworks design. It sits alongside public liability, workmen's compensation, Contractor's All Risk (CAR), and Erection All Risk (EAR). Cover limits are scaled to project value, with certificate copies provided in the contract documentation.
Can you do earthworks design and build on a JKR or federal project? +
Yes. CIDB G7 with CE01, CE08, and CE21 means we are eligible for JKR submissions with no upper tender value limit, and we have delivered federal corridor scope on projects such as EKVE and ECRL Section 3. Submissions go through the state JKR office and the project consulting engineer, aligned to JKR-SPJ Sections 2 and 7, BS 6031, and Eurocode 7. ESCP and DOE compliance are handled in the same package. This is project experience and eligibility, not panel registration.
Which integrated earthworks projects have you delivered? +
Integrated packages combining earthworks with retaining, slope, and drainage include Bandar Serendah in Hulu Selangor (540,000 m3 backfill, 7 retaining structures, including an industrial facility platform for a national automotive-industry account), Eco Terraces Phase 2 in Semenyih, Mukim Bandar Batu 18 (120,000 m3 earthworks plus 11,000 m2 retaining wall with soil nailing), and Alam Impian Township in Shah Alam (earthworks, soil improvement, soil nailing, retaining walls, drainage, and a flood detention pond across Precincts 6 to 10). Further platforms include Mukim Sentul, Bandar Ulu Kelang Spine Road, and Welbuilder Phase 5B. Client names are not disclosed.
09 / Related references

Where this connects.

Earthworks design and build brief?

Send the ground investigation or soil report, the survey or proposed platform layout, and the development brief. Same-day acknowledgement, with a design-and-build proposal covering cut and fill balance, retaining and slope scheme, drainage strategy, programme, and price. CIDB G7 + ISO 9001:2015 + PI insurance on the design.

Infraconcrete Construction Sdn Bhd
8B, Jalan SS22/25, Damansara Jaya, 47400 Petaling Jaya, Selangor, Malaysia
+60 16-428 1214 · WhatsApp · engineer@infraconcrete.co · Google Maps
CIDB G7 · ISO 9001:2015 · Sole STRATA Geosystems distributor in Malaysia (through Starwall Sdn Bhd)