Infraconcrete← Back to home
Soil nailing · QA/QC · BS 8081 Table 7

Soil nail pull-out test in Malaysia.

A working reference for consulting engineers, site engineers, and QS on soil nail pull-out testing in Malaysian projects. Five test types per BS 8081 Table 7 and BS 8006-2: investigation, suitability, acceptance, proof, and creep. Acceptance criteria, equipment setup, sample test report layout, common failure modes, and load-displacement curve interpretation. CIDB G7 in-house testing with calibrated load cells and ISO 9001:2015 traceable records. Federal corridor project experience: EKVE 450,000 m squared protected, ECRL Section 3 along 42 km and 64 km of alignment.

5 tests
BS 8081 Table 7 in-house
200-1000 kN
Hydraulic jack capacity range
Less than 1 mm
Creep limit between 1-10 min log-decade
G7
CIDB highest grade
Engineering note For soil nail pull-out testing across Malaysia, your point of contact is the Infraconcrete engineering desk. Send the spec, programme, and project location. Same-day quote with crew availability, calibration certificate copies, and price. WhatsApp the engineering desk →
01 / Five test types per BS 8081 Table 7

What each test actually verifies.

Test typePurposeWhenTypical frequency
InvestigationLoaded to failure on sacrificial nails to verify grout-soil bond and inform production nail spacing and lengthPre-production3-5 nails per site
SuitabilityConfirm production technique works on the actual site soil before mass mobilisationPre-production / early production1 in 30 nails or per 1000 m squared
AcceptanceProof load on production nails at 1.25-1.5 x DWL to confirm each nail meets design capacityProduction1 in 10 typical (1 in 5 or 1 in 6 federal corridor)
ProofProject-specific representative nail testingProductionPer consultant spec
CreepSustained-load displacement measurement per log-decade time to verify long-term performanceProduction (selected nails)Most loaded layer + deepest + one per stratum
02 / Acceptance criteria

What defines a PASS or FAIL.

CriterionThresholdReference
Test load achieved without bar yield1.25 to 1.5 x DWL (Design Working Load) typicalBS 8081 / BS 8006-2 / project spec
Total elastic + plastic displacement at test loadLess than 15 mm typical for residual soil sites at DWLProject spec, varies by ground
Creep displacement between 1 min and 10 min log-decade at 100 percent DWLLess than 1 mmBS 8081 Table 7 (mandatory)
Back-calculated bond stress meets or exceeds design assumptiontau_calc = F / (pi x d x L_b) greater than tau_designBS 8006-2 Section 6
Pre-loaded zero-reading repeatabilityWithin 5 percent on reloadBS 8081

Where DWL is the Design Working Load per the nail design calculation per BS 8006-2 (typical 100-300 kN for residential / commercial soil nail walls, 200-400 kN for federal corridor scope). tau_calc = test load divided by (pi x bar diameter x bond length).

03 / Test equipment register

What's deployed on a typical test.

EquipmentSpecification
Hydraulic hollow-ram jackCapacity 200-1000 kN depending on DWL. Calibration certificate dated within 6 months. Traceable to SIRIM or national standard.
Electronic load cellCalibrated digital load cell as primary measurement. Hydraulic pressure gauge as backup. Cross-check at each load step.
Displacement transducersLVDT (Linear Variable Differential Transformer) or dial gauges. Two for redundancy. Mounted on independent reference beam.
Reference beamAnchored to ground beyond influence zone (typical 3-5 m offset from test nail). Provides stable datum for displacement measurement.
Reaction frameBears on slope face through bearing plate. Steel I-beam or H-beam typical. Stiffness greater than 10 x bar stiffness to avoid frame deformation contaminating displacement reading.
Bearing platePlate area sized to distribute reaction load without facing damage. Typical 300 x 300 mm or 400 x 400 mm.
Hydraulic pumpManual control or programmable load schedule. Pressure stability less than 1 percent during sustained holds.
Data loggerTime-stamped pressure and displacement recording. ISO 9001:2015 traceable records. Daily backup.
04 / Sample test report layout

What the test report contains.

  1. Project identification: contract reference, project name, contract authority, test date, weather conditions, witness register.
  2. Nail identification: nail number, station / chainage / grid reference, slope face location, design working load (DWL), design grout-soil bond stress (tau_design), bar grade (Y20 / Y25 / Y32 or hollow bar R32-R76), bond length L_b, free length L_f, inclination angle below horizontal, drilling method (rotary auger / rotary percussion / self-drilling), grouting method (gravity / pressure), grout mix (water-cement ratio, additives), grouting date and time, time elapsed since grouting at test date.
  3. Equipment register: list of jack, load cell, LVDT, reference beam, calibration certificate numbers and dates.
  4. Test procedure: load schedule (cycle steps, hold times, increment magnitudes), pre-loading and zeroing procedure.
  5. Tabulated readings: load step, time of load application, load reading (kN), displacement reading 1 (mm), displacement reading 2 (mm), mean displacement (mm), notes.
  6. Load-displacement curve: graph with load on Y-axis, displacement on X-axis. Marked: linear elastic range, design working load, maximum test load, residual displacement after unload.
  7. Creep curve (for creep tests): displacement on Y-axis, log time on X-axis. Computed creep coefficient (alpha = delta_displacement per log-decade).
  8. Back-calculated bond stress: tau_calc = test load / (pi x bar diameter x bond length). Compared against tau_design.
  9. Acceptance determination: each criterion checked, PASS / FAIL marked, comments.
  10. Sign-off: testing engineer signature, date, submission for consulting engineer acceptance, witness signatures.
05 / Common failure modes

What goes wrong, and what it means.

Observed failureLikely causeAction
Premature pullout at low loadInadequate grouting (grout did not fill annulus); grout too young; bad bond zoneHold programme. Investigate grouting procedure. Re-grout or replace nail. Review pressure-grouting application.
Excessive displacement at design loadLower-than-assumed grout-soil bond stress; weaker ground than assumedDesign review. Possibly tighter spacing or longer bond length. Additional investigation tests in same zone.
Bar yielding before bond pulloutEither over-design (extra capacity, harmless) or under-design (rare; needs check)Verify bar grade. Cross-check design tensile capacity. May indicate over-conservative design.
Creep failure (greater than 1 mm per log-decade)Soft or weathered residual soil; insufficient grout cure time; very fine soil with viscous behaviourExtend cure time before next test. Reduce DWL for creep-prone ground. Adjust spacing.
Reaction frame movementEquipment issue, not nail performanceStiffer frame. Recheck reference beam anchorage.
Inconsistent results across nominally identical nailsGround heterogeneity (boulder, lens of weak material, varying weathering grade)Additional boreholes. Site-specific spacing adjustment.
06 / Load-displacement curve interpretation

How to read the graph.

  1. Linear elastic phase: initial steeply-sloped portion of the curve. Load-displacement relationship is roughly linear. Slope correlates with the composite stiffness of nail (bar) + grout + ground bond. Steeper slope = stiffer system.
  2. Yield onset: deviation from linear behaviour. May indicate initial plastic strain in the bond zone, micro-debonding, or bar yield (rare at DWL but possible at higher test loads).
  3. Plastic phase: shallower slope after yield onset. Bond zone progressively debonds or ground yields.
  4. Failure / asymptote: displacement increases rapidly at near-constant load. Either bond pullout (more displacement at same load) or bar yield (load drop with increasing displacement).
  5. Unload curve: residual displacement after unload. Indicates the proportion of plastic vs elastic deformation. Per BS 8081: residual displacement after unload at any test load should not exceed 50 percent of total displacement at that load.
  6. Reload (where conducted): reload zero should match original zero within 5 percent (per BS 8081). Significant mismatch indicates instrumentation drift or frame yielding.
07 / Standards register

What governs each test.

StandardSection / coverage
BS 8081:2015+A2:2018Table 7 specifies five test types and creep limit (less than 1 mm between 1-10 min log-decade)
BS 8006-2:2011Section 6 covers soil nail testing methodology
FHWA-NHI-14-007US methodology cross-referenced in Malaysian practice
BS EN 14490:2010Execution of special geotechnical works, soil nailing
JKR Slope Engineering ManualMalaysian federal-works alignment
JKR-SPJ Section 7Earthworks and slope, federal road and government building works
SIRIM / national calibration standardsEquipment calibration certificate traceability
ISO 9001:2015Quality management and traceable records for test documentation
08 / FAQ

Engineers and QS usually ask:

Can you provide independent third-party witnessing? +
Yes. Routine for federal corridor scope. Independent third-party witness (consultant geotechnical engineer or appointed third-party testing house) attends the test, signs the record, and verifies acceptance against criteria. Cost for independent witness arranged separately or included per consultant spec.
What if a test fails the acceptance criteria? +
Standard escalation. (1) Re-test on adjacent nail to rule out localised cause. (2) If failure pattern confirmed: hold subsequent production batch, investigate root cause, design review with consultant. (3) Remedial action: tighter spacing, longer length, alternative grouting method, or replacement of failed nail with adjacent compensating nail per consultant approval. (4) Documentation: failure report submitted to consultant with proposed remedial action and revised QA programme.
How long does a creep test take? +
Standard creep test sequence per BS 8081: load to DWL, hold for log-time sequence 1 min, 5 min, 10 min, 30 min, 60 min, 6 hr, 24 hr (or per project spec). Total test duration typically 1 to 25 hours depending on spec. Multi-load creep tests at multiple DWL fractions extend further. Scheduling considers nail accessibility, weather windows, and witness availability.
How quickly can you mobilise a pull-out test crew? +
Klang Valley: 24-48 hours from instruction. Other West Malaysia states: 48-72 hours. East Malaysia: 5-7 days project-specific. Calibration certificates of all equipment confirmed in advance with consulting engineer. ISO 9001:2015 traceable records on every test.
Do you do test-rig calibration on site? +
Calibration is done off-site at certified calibration houses (SIRIM-traceable). Calibration certificate dated within 6 months is mandatory. On-site we check baseline-zero stability before each test, cross-check pressure gauge against electronic load cell, and verify reference beam stability. Pre-test setup checks documented in the test report.
09 / Related references

Where this connects.

Need soil nail pull-out testing?

Send spec + programme + project location. Same-day quote with crew availability, calibration certificate copies, and price. CIDB G7 + ISO 9001:2015 + EKVE / ECRL track record.