Infraconcrete
Ground Anchor · Specialist Contractor

Ground anchor contractor.

Specialist ground anchor contractor for high retaining walls (over 12 m), deep excavation propping, dam tie-back, and high-load slope reinforcement. Post-tensioned permanent and temporary anchors with working loads typically 500-1500 kN. To BS 8081, EN 1537, AASHTO. Calibrated grouting protocol, load-tested at 1.5x design. CIDB G7, ISO 9001:2015.

500-1500 kN
Working load range
BS 8081
Standards native
100+
Projects delivered
G7
CIDB highest
Engineer's note Multi-strand or threadbar ground anchors (4-12 strand 600-2000 kN typical) take the high-load slope reinforcement cases. Bond zone in competent rock, free length through retained mass, pre-tensioned at head. Class 2 dual-corrosion for permanent / aggressive ground. Send the anchored wall design for input. WhatsApp the engineering team →
01 / What is a ground anchor

Tensioned tendon transferring load to competent strata.

A ground anchor (also called a post-tensioned soil/rock anchor) is a high-capacity tensile element drilled into the ground, grouted into a bond zone in competent strata, then post-tensioned to lock load into the structure being restrained. Unlike soil nails (passive, smaller, shorter), ground anchors are active (pre-stressed) and engineered for much higher loads - typically 500-1500 kN working load.

Ground anchors are used when soil nailing is not enough: very high retaining walls, deep excavation propping under buildings, dam tie-back retrofits, post-failure slope reinforcement on critical assets. Each anchor is individually load-tested before being put into service.

02 / Ground anchor scope we deliver

Permanent and temporary anchors, full installation cycle.

Permanent anchors

Double-corrosion-protected (DCP) tendon (multistrand or single bar). Cement grout bond zone in competent strata. Free length sleeved + greased. Anchor head with bearing plate + locking system. Design life 75-120 years. Used on permanent retaining walls, anchored bored-pile walls.

Temporary anchors

Single-corrosion-protected tendon. Cement grout bond zone. Used during deep excavation to prop sheet-pile or contiguous-bored-pile walls until permanent structure is in place. De-tensioned and abandoned at end of service.

Drilling + grouting

Rotary or rotary-percussive drilling to bond-zone depth (typically 8-25 m). Cement grout pumped under controlled pressure. Bond zone tested for capacity before tendon installation.

Stressing + lock-off

Stressed to 125% design load (proof test) then locked off at 100%. Full load-deflection curve recorded for QA report. Suitable for federal / authority submission.

03 / Where ground anchors apply

Five common Malaysian ground anchor use cases.

1. High retaining walls

Walls over 8-12 m height where soil nail / RC cantilever / MSE alone won't satisfy stability. Anchored RC or sheet-pile walls common in deep highway cuts.

2. Deep excavation propping

Basement excavations 8-25 m deep, contiguous-bored-pile or secant walls anchored back into competent strata to prevent inward deflection.

3. Post-failure slope reinforcement

When standard soil nails are insufficient (slip surface very deep, very high required capacity). High-capacity anchors stitched across the failure plane.

4. Hill-station / federal expressway cuts

Genting / Cameron / EKVE-style very high cuts where slope geometry forces anchored solutions for slope stability.

04 / Anchor Types

Permanent and temporary, strand and bar.

Ground anchors split into four broad families by tendon type, end fixity, and design life. Selection is driven by working load, design life, ground type, and corrosion exposure.

Strand anchors (high-capacity, the federal default)

Multi-strand tendons made up of 4 to 12 strands of seven-wire prestressing steel (15.2 mm or 15.7 mm nominal diameter per strand, 1860 N/mm² tensile strength per BS 5896). Used for high working loads (500 to 2000 kN per anchor typical, exceptionally up to 3000 kN). The default for highway retaining walls, deep basement walls, anchored bridge abutments, and post-failure high-load remediation. Tendons greased and HDPE-sheathed inside the free length so the strand can elongate freely under prestressing load.

Bar anchors (medium-capacity, fast install)

Single high-yield steel bar tendon. Y32 deformed (BS 4449), 26.5 to 50 mm deformed threadbar (DIN 488), or self-drilling hollow bar (R32, R38, R51, R76). Working capacity typically 100 to 600 kN per anchor. Used for medium-load retaining walls, slope reinforcement deeper than soil-nail economics allow, and tunnel portal stabilisation. Faster to install than strand because the tendon is a single bar rather than a bundle.

Permanent versus temporary

Temporary anchors: design life less than 2 years (basement excavation propping during construction, deep cut support during phasing). Single Corrosion Protection (SCP) acceptable per BS 8081. Permanent anchors: design life 50+ years (retaining wall tieback, slope stabilisation). Double Corrosion Protection (DCP) per BS 8081 Table 5 in aggressive ground, SCP elsewhere. Aggressive ground = high sulphate, low pH, salt-spray, contaminated water.

Tensioned versus untensioned

Ground anchors are almost always tensioned (pre-loaded against a bearing plate or anchorage block at the structure). Lock-off load typically 50 to 75 percent of the characteristic tendon yield. Tensioning is the whole point: it actively pulls the structure back into the soil mass, reducing displacement and improving stability factor. Untensioned (passive) is reserved for specific cases where pre-load is undesirable.

05 / Materials and Specifications

Tendon, hole, grout, anchorage.

ParameterTypical specificationStandard
Tendon (strand)4 to 12 strands x 15.2 or 15.7 mm, 1860 N/mm²BS 5896 / ASTM A416
Tendon (bar)Y32 / 26.5 to 50 mm threadbar / R32 to R76 SDABS 4449, DIN 488, manufacturer cert
Working capacity100 to 2000 kN (typical), up to 3000 kNPer design
Anchor length10 to 50 m typical, with bond length 5 to 12 mPer design
Hole diameter110 to 200 mm typicalPer design
Inclination10 to 45 degrees below horizontalPer design
Grout (primary)w/c 0.40 to 0.45, 28-day strength 30 to 40 N/mm²BS EN 445 / 446 / 447
Pressure grouting (where required)5 to 30 bar tube-a-manchette for bond enhancementBS EN 1537 Annex A
Free length sheathing (strand)HDPE smooth sheath with grease infillBS 8081 Table 5
Corrosion protection (SCP)Cement grout cover plus one barrierBS 8081 Table 5
Corrosion protection (DCP)HDPE corrugated outer plus inner cement groutBS 8081 Table 5
Bearing plateSteel domed or flat, 200 to 400 mm square typicalPer design
Lock-off load50 to 75 percent of characteristic yieldBS 8081
06 / Method of Installation

Drill, insert, grout, stress, verify.

Stage 1: Set-out and design verification

Anchor pattern set out to the design grid. ITP (Inspection and Test Plan), HIRARC, method statement, traffic management plan submitted before mobilisation. Design loads, anchor length, bond length, free length, and inclination cross-checked against ground conditions reported in the borehole logs.

Stage 2: Drilling

Track-mounted or skid-mounted drill rig positioned at each anchor location. Cased drilling in unstable ground (temporary casing supports the hole), open-hole drilling in competent strata. Drill at the design inclination to design depth. Cuttings flushed by air, water, or polymer mud per ground type.

Stage 3: Tendon assembly and insertion

Strand bundle assembled with the bond-length section bare (for grout contact) and the free-length section greased and HDPE-sheathed (so strands can elongate freely during stressing). Bar tendons fitted with centralisers, anti-bonding sleeves over the free length. Tendon inserted to design depth with grout tubes attached.

Stage 4: Primary grouting

Cement grout tremied from the back of the hole forward to surface, displacing drill fluid. Grout cement-water ratio per spec (typical 0.40 to 0.45). Where higher bond capacity is required (loose granular, weathered rock with low bond), tube-a-manchette pressure grouting applied at 5 to 30 bar to fracture-grout the bond zone for enhanced shaft friction.

Stage 5: Grout cure and bearing-plate fit

Primary grout cured to specified strength (typically 7 days for design load, 28 days for full strength). Bearing plate, anchorage head, and stressing jack fitted at the face.

Stage 6: Stressing and lock-off

Hydraulic jack tensions the tendon in stages per the spec. Load and extension measured at each stage and plotted against the design elastic line. Acceptance criteria per BS 8081: elastic extension within tolerance, creep within allowable, no slippage. Lock-off at design load (50 to 75 percent of characteristic yield). Excess tendon cut and capped with protective cover.

Stage 7: Acceptance testing

Investigation tests on sacrificial anchors at the start of works (loaded to failure to verify ultimate bond capacity in the actual ground). Suitability tests on production-method anchors (proof load with extended sustained-load hold per BS 8081 Table 7). Acceptance tests on 100 percent of production anchors at proof load (typically 1.25 to 1.5 times design working load per BS 8081, sustained for 5 to 15 minutes, creep no greater than allowable). Failed anchors rejected and remedial anchors installed.

Stage 8: Lift-off testing (long-term monitoring)

For permanent works, periodic lift-off testing on representative anchors over the design life. Verifies that the tendon is still carrying the design load and has not relaxed beyond allowable. Schedule per BS 8081 / design code, typically year 1, 5, 10, 25, 50.

07 / Standards, Testing, QA

The code framework that governs every anchor.

Design and execution

BS 8081 Code of Practice for Ground Anchorages (the primary UK reference). BS EN 1537 Execution of Special Geotechnical Work, Ground Anchors (the European execution standard). BS EN 1997-1 Eurocode 7 Geotechnical Design. FHWA-IF-99-015 Geotechnical Engineering Circular No 4, Ground Anchors and Anchored Systems (US Federal Highway). AASHTO LRFD Bridge Design Specifications Section 11 (US Federal reference for tieback walls). JKR Standard Specification for Malaysian government works.

Materials standards

BS 5896 (seven-wire prestressing steel strand), ASTM A416 (US equivalent), BS 4449 (deformed reinforcing steel), DIN 488 (German rebar including threadbar), BS EN 10080 (weldable reinforcing), BS EN 445 / 446 / 447 (cementitious grouts), BS EN 14199 (micropiles, related execution).

Testing per BS 8081 (three test types)

  • Investigation tests: sacrificial anchors loaded to failure at the start of the project to verify ultimate bond capacity in the actual ground. Typically 3 to 5 per anchor zone.
  • Suitability tests: proof loading of production-method anchors with extended sustained-load hold to verify creep and constructability. Typically 1 in 5 to 1 in 10 of early production anchors.
  • Acceptance tests: proof loading of 100 percent of production anchors at typically 1.25 to 1.5 times design working load, sustained for 5 to 15 minutes per BS 8081 Table 7. Anchors failing the acceptance criteria are rejected and replaced.

SCP versus DCP (corrosion protection selection)

Single Corrosion Protection sufficient for design life less than 50 years in low-aggressivity ground (typical residual soils, neutral pH). Double Corrosion Protection required for design life 50+ years OR aggressive ground (high sulphate, low pH, salt-spray, contaminated). Aggressivity assessment per BS 8081 Table 5 cross-referenced with ground chemistry from the SI report.

08 / Mobilisation

Crew, equipment, programme.

Typical core crew: 1 supervisor, 4 to 8 anchor crew (drill operators, helper, grouter, stressing technician), 1 rope-access technician (for face-anchor zones), 1 safety officer, 1 surveyor. Equipment: track-mounted specialist anchor / micropile drilling rig sized to anchor length and ground type, grout plant (colloidal cement-water mixer plus piston pump, optionally tube-a-manchette pressure-grouting rig at 5 to 30 bar), hydraulic stressing jacks rated to design load (typically 1000 to 3000 kN capacity), calibrated load cells for proof-load verification, survey equipment, digital data logger for stressing curves. Standard production rate: 1 to 3 anchors per day per crew depending on length and ground type. Mobilisation 2 to 4 weeks from contract signature.

09 / FAQ

What engineers usually ask first.

What is a ground anchor / tieback? +
A ground anchor (post-tensioned soil or rock anchor, also called tieback) is a high-capacity tensile element drilled into the ground, grouted into a bond zone in competent strata, then post-tensioned to lock load into the structure being restrained. Unlike soil nails (passive, smaller, shorter), ground anchors are active (pre-stressed) and engineered for high loads ,typically 500 to 2000 kN working load.
When are ground anchors required instead of soil nails? +
Soil nails (passive, 100-300 kN, 6-15 m) suit cut slopes, basements, and distressed slope remediation. Ground anchors (active, 500-2000 kN, 15-40 m) are required for very high retaining walls (>12 m), deep excavation propping where the wall must hold against full active earth pressure, dam tieback, post-failure slope reinforcement on critical assets, and bridge abutment tiedown.
Strand or bar anchor? +
Strand anchors: 4-12 strands of 7-wire 15.2 or 15.7 mm prestressing steel (1860 N/mm² per BS 5896 / ASTM A416). Working capacity 500-2000 kN, exceptionally to 3000 kN. Federal default. Bar anchors: single Y32 deformed bar (BS 4449), 26.5-50 mm threadbar (DIN 488), or self-drilling hollow bar (R32 / R38 / R51 / R76). Working capacity 100-600 kN. Faster install. Used for medium-load walls and tunnel portal works.
What is tube-a-manchette pressure grouting? +
TAM is controlled pressure-grouting used where standard primary grouting gives insufficient bond. A perforated grout tube with one-way valves (manchettes) at intervals along the bond zone is installed with the tendon. After primary grouting, secondary grout is pumped through the TAM at 5-30 bar (BS EN 1537 Annex A) to fracture-grout the surrounding soil or weathered rock, increasing effective bond zone diameter and shaft friction. Standard for high-load anchors in weathered rock or loose granular ground.
Investigation / suitability / acceptance / creep / lift-off tests? +
BS 8081 / BS EN 1537 / FHWA-IF-99-015 five test types. Investigation: sacrificial anchors loaded to failure pre-production. Suitability: proof loading with extended hold for creep verification. Acceptance: 100% of production anchors proof-loaded at 1.25-1.5x design working load, 5-15 min hold. Creep test: displacement at 1, 5, 15, 30, 60 min per EN 1537; acceptance ≤ 1 mm at 50% proof load. Lift-off: periodic re-testing on permanent anchors (year 1, 5, 10, 25, 50) to verify tendon is still carrying design load.
FHWA / AASHTO proof load schedule? +
Standard stage schedule per FHWA-IF-99-015 / AASHTO LRFD: 0.10, 0.25, 0.50, 0.75, 1.00, 1.20, 1.33 x design working load with hold times at each step. Max test load 80% GUTS per BS 8081. Lock-off at 0.60-0.70 of design working load after creep verified within allowable.
SCP or DCP corrosion protection? +
SCP (Single Corrosion Protection): design life < 50 years in low-aggressivity ground (pH 6-10, resistivity > 5000 ohm-m, chloride < 200 mg/kg, sulphate < 1000 mg/kg). DCP (Double Corrosion Protection): design life 50+ years or aggressive ground per BS 8081 Table 5. DCP uses outer HDPE corrugated sheath grouted around inner cement-grouted tendon (two independent barriers). Aggressivity assessment drives selection.
Bond length, free length, total length? +
Fixed anchor (bond) length: cement-grouted segment in competent strata, 5-12 m typical (minimum 3 m per BS 8081). Free (stressing) length: from bond zone to bearing plate, sheathed in smooth HDPE bond breaker with grease for elastic stretch under prestressing. Total tendon 10-50 m typical, dictated by location of competent bond stratum and retained-structure geometry.
Hardware at the head? +
Steel bearing plate (200-400 mm square, 25-40 mm thick, hot-dip galvanised for permanent), anchor head with wedge plate / threaded coupler for stressing and lock-off, hemispherical bevel washer for inclined heads, HDPE protective cap with corrosion-inhibiting grease over the lock-off head (permanent anchors). Concrete capping beam or steel waling beam transfers load from individual heads to the retained wall.
Installation near sensitive structures? +
Vibration-controlled rotary drilling (no percussion), cased boreholes, real-time vibration monitoring on adjacent buildings, controlled grouting pressure to prevent ground heave or hydrofracturing into utilities, settlement monitoring throughout works. Standard practice on urban basement works adjacent to occupied buildings.
Ground anchor in Bahasa Malaysia (sauh tanah)? +
Ya. Kontraktor sauh tanah pakar di Malaysia. CIDB G7, ISO 9001:2015. Sauh tanah tertegang kekal dan sementara, multi-strand dan bar, mengikut BS 8081, BS EN 1537, FHWA-IF-99-015, AASHTO LRFD, JKR. Hubungi WhatsApp +60 16-428 1214 atau /bm/sauh-tanah/.
What does a ground anchor cost? +
Quoted per anchor by working load and length: 4-strand 600-700 kN typical RM 15,000-25,000; 6-strand 900-1000 kN RM 22,000-35,000; 8-strand 1300-1400 kN RM 30,000-50,000; 12-strand 1900-2000 kN RM 50,000-80,000. Per m² anchored wall face RM 800-2500. Class 2 DCP adds 20-30%. Excludes RC capping beam. Send geometry on WhatsApp for same-day budget.

Ground anchor scope on your project?

High retaining wall, deep excavation, post-failure remediation. Same-day brief acknowledgement.

More from Infraconcrete

Continue exploring.

Regional coverage for Ground Anchor / Tieback

Ground Anchor / Tieback contractor service across Malaysia. Click your state for the regional combo page, or scroll the locality cards for dedicated city / town pages:

States:Klang Valley (KL, Selangor, Putrajaya) · Johor · Penang · Pahang · Sabah · Sarawak

Klang Valley localities:Klang Valley regional hub · PJ · Cheras · Kajang · Subang Jaya · Shah Alam · Mont Kiara · Damansara · Puchong · Klang · Cyberjaya · Putrajaya · Bukit Jalil · Bangsar · Setapak · Kepong · Ampang · Selayang · Semenyih · Hulu Selangor · Bandar Sunway · USJ

Johor: Iskandar Puteri · Pasir Gudang · JB · Senai · Skudai · Kulai · Batu Pahat · Muar · Kluang · Mersing

Penang: George Town · Bayan Lepas · Butterworth · Bukit Mertajam · Tanjung Bungah · Air Itam · Balik Pulau

Other states: Kuantan · Genting Highlands · Cameron Highlands · KK · Sandakan · Tawau · Kuching · Miri · Sibu · Bintulu · Ipoh · Seremban · Bandar Melaka · Alor Setar · Kota Bharu · Kuala Terengganu · Kangar

Infraconcrete Construction Sdn Bhd
8B, Jalan SS22/25, Damansara Jaya, 47400 Petaling Jaya, Selangor, Malaysia
+60 16-428 1214 · WhatsApp · engineer@infraconcrete.co · Google Maps
CIDB G7 · ISO 9001:2015 · Sole STRATA Geosystems distributor in Malaysia (through Starwall Sdn Bhd)